Spanning across 103km with 264 towers, the project connects Mowaih and Hodn in Saudi Arabia.
May 15, 2026

KEC International Limited has completed the successful installation of a 380kV double circuit transmission line, connecting Mowaih PV BSP and Hodn PV BSP in Saudi Arabia. This project strengthens the transmission network in the region , enabling RE integration and energy transmission.
Also Read: HFCL Bags Over INR 183 Crore Export Orders for Optical Fibre Cables
Spanning across 103km with 264 towers, the project showcases safety, quality and on-ground execution, building a sustainable infrastructure in the Middle Eastern region.