VBB Infra Private Limited has secured a contract from Power Grid Corporation of India Limited (PGCIL) for reconductoring the Lara–Raigarh (Kotra) 400 kV double-circuit line in Chhattisgarh, with completion scheduled within 10 months.
Nov 4, 2026

VBB Infra Private Limited has won the Reconductoring Package OH01 contract for upgrading the existing Lara-l -Raigarh (Kotra) 400 kV double-circuit transmission line in Chhattisgarh.
Watch: Top Cable Companies in India
The project involves replacing the existing conductors with twin high-temperature low-sag (HTLS) conductors, with a minimum capacity of 2,100 MVA per circuit at nominal voltage. The work is associated with schemes to address high loading on the transmission line and is expected to be completed within 10 months.
Also Read: Viviana Power Tech Secures INR 466.74 Crore Turnkey Contracts from MGVCL
PGCIL invited bids for the project in April 2026. VBB Infra secured the contract on October 29, 2026.