Kalpataru Projects International Limited completes 765 kV and 400 kV transmission projects for Resonia Limited, strengthening Rajasthan’s power transmission infrastructure.
Jul 29, 2026

Kalpataru Projects International Limited has successfully completed and energized 765 kV and 400 kV double-circuit transmission lines in Rajasthan for Resonia Limited, marking a significant milestone in its power transmission portfolio.
Watch: Top Cable Companies in India
The project covers a total line length of 101.39 km and includes the 765 kV D/C LILO Ajmer–Chittorgarh Transmission Line (68.30 km), energized on 23 July 2026, and the 400 kV D/C LILO Kota–Merta Transmission Line (33.09 km), energized on 3 April 2026.
Also Read: KEC International Strengthens Partnership with Guinea on Power Transmission Development
Executed across challenging rocky terrain between Ajmer and Beawar, the project involved complex foundation works, controlled blasting, and drilling activities. The team also managed execution challenges arising from heavy rainfall, waterlogging, and seepage at multiple locations.